What would be the thickness for the pavement if the CBR value of the soil is found out to be 20% and the traffic is estimated to be 4300 commercial vehicles per day? |
| A. | 30 cm |
| B. | 20 cm |
| C. | 22 cm |
| D. | 25 cm |
| Answer» C. 22 cm | |