1.

The treatment system includes a WAC, SAC, followed by a WBA and SBA. There is a degasser in this system. Calculate the amount of SBA resin required for the following data.M Alkalinity: 100 ppm as CaCO3P Alkalinity: 100 ppm as CaCO3Silica: 30 ppm as CaCO3CO2: 45 ppm as CaCO3EMA: 100 ppm as CaCO3Capacity: 37 Kg/m3Correction factor: 0.9Flow rate: 35 m3/hrOperation hours: 10 hrs

A. 0.5 m3
B. 0.9 m3
C. 1.9 m3
D. 1.5 m3
Answer» B. 0.9 m3


Discussion

No Comment Found