%_The reduction in project time normally results in_% |
A. | Decreasing the direct cost and increasing indirect cost |
B. | Increasing the direct cost and decreasing the indirect cost |
C. | Increasing the direct cost and indirect cost both |
D. | Decreasing the direct cost and indirect cost both |
Answer» C. Increasing the direct cost and indirect cost both | |