MCQOPTIONS
Saved Bookmarks
| 1. |
The reduction in project time normally results in |
| A. | Decreasing the direct cost and increasing indirect cost |
| B. | Increasing the direct cost and decreasing the indirect cost |
| C. | Increasing the direct cost and indirect cost both |
| D. | Decreasing the direct cost and indirect cost both |
| Answer» C. Increasing the direct cost and indirect cost both | |