MCQOPTIONS
 Saved Bookmarks
				| 1. | 
                                    The quantity of coarse aggregate required for RCC (1:3:6) for 20 cubic metres of work is ________ | 
                            
| A. | 18.24 m3 | 
| B. | 15.23 m3 | 
| C. | 24.87 m3 | 
| D. | 32.45 m3 | 
| Answer» B. 15.23 m3 | |