Explore topic-wise MCQs in Testing Subject.

This section includes 657 Mcqs, each offering curated multiple-choice questions to sharpen your Testing Subject knowledge and support exam preparation. Choose a topic below to get started.

1.

In the cubical contents method, the cost of a structure is computed by the multiplication of total cubic contents and _______

A. Area of building
B. Volume of building
C. Local cubic rate
D. Length of building
Answer» D. Length of building
2.

In the plinth area method, the cost of construction is computed by the multiplication of ________

A. Plinth length and rate
B. Plinth breadth and rate
C. Plinth area and plinth area rate
D. Plinth volume and plinth length rate
Answer» D. Plinth volume and plinth length rate
3.

In the case of works which require some special types of equipment, an amount of ______ percent of the estimated cost is given.

A. 1-2
B. 5-9
C. 12-18
D. 16-20
Answer» B. 5-9
4.

While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per __________

A. Special Data Book
B. Standard Data Book
C. Special Data Record
D. Specific Data Record
Answer» C. Special Data Record
5.

The process of working out the cost per unit of each item is known as _________

A. Work
B. Sheet
C. Data
D. Analysis
Answer» D. Analysis
Previous Next