1.
_The probability of completion of any activity within its expected time is$?
A.
50 %
B.
84.1 %
C.
99.9 %
D.
100 %
Answer» B. 84.1 %
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
Which one of the following is not an excavating and moving type of equipment?%!
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to%!
The area under the Beta distribution curve is divided into two equal parts by%!
Critical path method%!
Bar charts are suitable for%!
Updating may result in%!
In the given figure, the network of a project represents%!
Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is%!
In resources levelling%!
PERT is%!
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply
Your experience on this site will be improved by allowing cookies. Read
Cookie Policy
Reject
Allow cookies