MCQOPTIONS
Saved Bookmarks
1. |
The optimistic, most likely and pessimistic time estimates of an activity are 5, 10 and 21 days respectively. What are the expected time and standard deviation ? |
A. | 12, 3 |
B. | 11, 4 |
C. | 11, |
D. | 10, 16 |
Answer» D. 10, 16 | |