The optimistic, most likely and pessimistic time estimates of an activity are 5, 10 and 21 days respectively. What are the expected time and standard deviation ? |
| A. | 12, 3 |
| B. | 11, 4 |
| C. | 11, |
| D. | 10, 16 |
| Answer» D. 10, 16 | |