The optimistic, most likely, and pessimistic estimates of time for an activity are 4 days, 11 days and 12 days respectively. The expected completion time of this activity is |
A. | 8 days |
B. | 9 days |
C. | 10 days |
D. | 11 days |
Answer» D. 11 days | |