The normal duration and normal cost of an activity are 10 days and Rs 350/- respectively. The cost slope is Rs 75/- per day. If the crash duration is 8 days, then what is the crash cost of the activity ? |
A. | Rs 400/- |
B. | Rs 500/- |
C. | Rs 600/- |
D. | None of these |
Answer» C. Rs 600/- | |