The individual part of the structures is subjected to a load test for 24 hours by applying a load equal to full dead load of the structure plus |
A. | imposed load |
B. | 1.15 times imposed load |
C. | 1.25 times imposed load |
D. | 1.3 times imposed load. |
Answer» D. 1.3 times imposed load. | |