The flownet of activities of a project is shown in the given figure. The duration of the activities are written along the arrows. The critical path of the activities is along |
A. | 1-2-4-5-7-8 |
B. | 1-2-3-5-7-8 |
C. | 1-2-3-6-7-8 |
D. | 1-2-4-5-3-6-7-8 |
Answer» C. 1-2-3-6-7-8 | |