The correct sequence, in the direction of the flow of water for installations in the hydro-power plant is |
| A. | reservoir, surge tank turbine, penstock |
| B. | reservoir, penstock, surge tank, turbine |
| C. | reservoir, penstock, turbine, surge tank |
| D. | reservoir, surge tank, penstock, turbine |
| Answer» C. reservoir, penstock, turbine, surge tank | |