MCQOPTIONS
Saved Bookmarks
1. |
The correct sequence, in the direction of the flow of water for installations in the hydro-power plant is |
A. | reservoir, surge tank turbine, penstock |
B. | reservoir, penstock, surge tank, turbine |
C. | reservoir, penstock, turbine, surge tank |
D. | reservoir, surge tank, penstock, turbine |
Answer» C. reservoir, penstock, turbine, surge tank | |