MCQOPTIONS
Saved Bookmarks
1. |
The construction manager uses the estimate of the project |
A. | to tell the owner of the project to take his/her financial decision. |
B. | to advise the architect/engineer regarding design cost parameter especially in value engineering analysis. |
C. | to develop bids on the project. |
D. | to control the project during its construction. |
Answer» E. | |