*/*_The area is measured correct to the nearest?..
1.
*/*_The area is measured correct to the nearest?
A.
0.01 sqm
B.
0.02 sqm
C.
0.03 sqm
D.
0.04 sqm
Answer» B. 0.02 sqm
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
While estimating a reinforced cement structure, the omitted cover of concrete is assumed%!
The measurement is not made in square meters in case of%!
The expected out turn of half brick partition wall per mason per day is%!
The cross-sections for a highway is taken at%!
The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is%!
The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is%!
The detention period in a septic tank is assumed%!
While preparing a detailed estimate%!
Anti-siphonage pipe is connected to%!