MCQOPTIONS
Saved Bookmarks
| 1. |
The actual manufacturing overhead costs is $485000 and actual total quantity of cost allocation base is 4500 labor hours then the overhead rate is |
| A. | 109.87 |
| B. | $107.78 |
| C. | $106.56 |
| D. | $104.34 |
| Answer» C. $106.56 | |