The actual manufacturing overhead costs is $225000 and actual total quantity of cost allocation base is 2500 labor hours then the overhead rate is |
| A. | $60 |
| B. | $90 |
| C. | $80 |
| D. | $70 |
| Answer» C. $80 | |