1. |
Select the incorrect statement.$? |
A. | Earliest start of an activity is the early event time of the node it leaves |
B. | Latest finish of an activity is the late event time of the node it enters |
C. | Latest start of an activity is its latest finish minus its duration |
D. | None of the above |
Answer» E. | |