1. |
Select the correct statement.? |
A. | Quantity of binder required for tack coat is less than that required for prime coat. |
B. | Prime coat treatment is given for plugging the voids in water bound macadam during bituminous road construction. |
C. | Seal coat is the final coat over certain previous bituminous pavements. |
D. | A bitumen primer is a high viscosity cutback. |
Answer» E. | |