Removal of props under |
A. | slabs spanning upto 4.5 m is 7 days |
B. | slabs spanning more than 4.5 m is 14 days |
C. | beams spanning upto 6 m is 14 days |
D. | beams spanning more than 6 m is 21 days |
Answer» E. | |