Removal of props under______________? |
| A. | slabs spanning upto 4.5 m is 14 days |
| B. | beams spanning upto 6 m is 14 days |
| C. | slabs spanning upto 4.5 m is 7 days |
| D. | All the above |
| Answer» E. | |