1.

_In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having$?

A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer» D. Shortest duration