1.

In the network given in figure, the maximum number of shovels and dumpers required are

A. 6 shovels and 14 dumpers on days 9 and 10
B. 24 shovels and 10 dumpers on days 3 and 4
C. 30 shovels and 90 dumpers on all days
D. 10 shovels and 24 dumpers on days 3 and 4
Answer» E.