In the method of voids for determination of the quantity of cement paste, it is assumed that |
A. | voids in coarse aggregates are filled by fine aggregates |
B. | voids in fine aggregates are filled by the cement paste |
C. | volume of fine aggregates is equal to total voids in coarse aggregates plus 10% extra |
D. | all the above |
Answer» E. | |