In PERT, the actual time duration along the critical path for the project completion time is probabilistic. It is usually presumed to follow which one of the following ? |
| A. | Beta distribution |
| B. | Poisson distribution |
| C. | Normal distribution |
| D. | Log-normal distribution. |
| Answer» B. Poisson distribution | |