In PERT, the actual time duration along the critical path for the project completion time is probabilistic. It is usually presumed to follow which one of the following ?

A. Beta distribution
B. Poisson distribution
C. Normal distribution
D. Log-normal distribution.
Answer» B. Poisson distribution