In "full face" method of constructing tunnel, the first operation relates to |
A. | removal to bottom portion |
B. | excavation of one drift in the centre |
C. | removal of top portion |
D. | excavation being done along the perimeter |
Answer» D. excavation being done along the perimeter | |