In case of big projects, a certain amount to the extent of about 1.5% to 2% of the estimated cost is provided in the estimate as |
| A. | Work charged establishment |
| B. | Revised estimates |
| C. | Supplementary estimate |
| D. | Annual estimate |
| Answer» B. Revised estimates | |