1.

In a project logic, four activities M, N, O and P are required to be completed before starting activity Q. If the finish times of M, N, O and P are 12 days, 14 days, 15 days and 17 days respectively, the earliest event occurrence time for the activity Q is

A. 12 days
B. 14 days
C. 15 days
D. 17 days
Answer» E.