In a project logic, four activities , , and are required to be completed before starting activity . If the finish times of , , and are 12 days, 14 days, 15 days and 17 days respectively, the earliest event occurrence time for the activity is |
| A. | 12 days |
| B. | 14 days |
| C. | 15 days |
| D. | 17 days |
| Answer» E. | |