MCQOPTIONS
Saved Bookmarks
| 1. |
In a pert activity, optimistic time is 5 hr, pessimistic time is 20 hr and the most likely time is 10 hr then what is the expected time for completion of the activity (in hours)? |
| A. | 11.13 |
| B. | 10.833 |
| C. | 9 |
| D. | 10 |
| Answer» C. 9 | |