In a company assembly line, assembling gear boxes, five workers are assigned tasks who take 10, 8, 6, 9 and 10 minutes respectively. The balance delay for this assembly line is

A. 13.3%
B. 14.0%
C. 16.0%
D. 43.3%
Answer» C. 16.0%