If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then |
| A. | expected time of activity A is greater than the expected time of activity B |
| B. | expected time of activity B is greater than the expected time of activity A |
| C. | expected time of both activities A and B are same |
| D. | none of the above |
| Answer» D. none of the above | |