1.

If the duration of activity f alone is changed from 9 to 10 days, then the

A. Critical path remains the same and the total duration to complete the projectChanges to 19 days.
B. Critical path and the total duration to complete the project remain the same.
C. Critical path changes but the total duration to complete the project remains the same.
D. Critical path changes and the total duration to complete the project changes to 17 days.
Answer» B. Critical path and the total duration to complete the project remain the same.


Discussion

No Comment Found