If the duration of activity f alone is changed from 9 to 10 days, then the |
| A. | Critical path remains the same and the total duration to complete the projectChanges to 19 days. |
| B. | Critical path and the total duration to complete the project remain the same. |
| C. | Critical path changes but the total duration to complete the project remains the same. |
| D. | Critical path changes and the total duration to complete the project changes to 17 days. |
| Answer» B. Critical path and the total duration to complete the project remain the same. | |