If standard hours are 400 @ Rs. 1 per hour and actual hours are 380 @ Rs. 1.25 perhour, the labour rate variance is:

A. Rs. 20 (Favourable)
B. Rs. 25 (Favourable)
C. Rs. 100 (Adverse)
D. Rs. 95 (Adverse)
Answer» E.