1.
For the network shown in the given figure, the expected time for the activity%!
A.
1-2 is 4
B.
2-3 is 7
C.
3-4 is 8
D.
All the above
Answer» E.
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
Which one of the following is not an excavating and moving type of equipment?%!
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to%!
The area under the Beta distribution curve is divided into two equal parts by%!
Critical path method%!
Bar charts are suitable for%!
Updating may result in%!
In the given figure, the network of a project represents%!
Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is%!
In resources levelling%!
PERT is%!