For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is |
A. | Dry rolling, wet rolling, application of screening and application of filler |
B. | Dry rolling, application of filler, wet rolling and application of screening |
C. | Dry rolling, application of screening, wet rolling and application of filler |
D. | Dry rolling, application of screening, application of filler and wet rolling |
Answer» D. Dry rolling, application of screening, application of filler and wet rolling | |