MCQOPTIONS
Saved Bookmarks
| 1. |
For sanitary and water supply works, what percentage of the estimated cost of the building works are usually provided in an estimate? |
| A. | 8% for sanitary work and 7% for water supply work |
| B. | 8% for sanitary work and 8% for water supply work |
| C. | 7% for sanitary work and 8% for water supply work |
| D. | 7% for sanitary work and 7% water supply work |
| Answer» C. 7% for sanitary work and 8% for water supply work | |