For event 1, the earliest occurrence time is 8 weeks and the latest occurrence time is 26 weeks. For event 2, the earliest occurrence time is 32 weeks and the latest occurrence time is 37 weeks. If the activity time is 11 weeks, the total float will be:

A. 11
B. 13
C. 18
D. 24
Answer» D. 24