For an activity the pessimistic, most likely and optimistic time are 10 days, 6 days and 2 days respectively. The expected duration of activity based on Beta distribution will be: |
| A. | 6 days |
| B. | 3 days |
| C. | 2 days |
| D. | 9 days |
| Answer» B. 3 days | |