| 1. |
For a given process control chart, there are four rules for determining out- of-control state of the process which are being used simultaneously. The probability of Type-I error for the four rules are 0.005, 0.02, 0.03, and 0.05. Assuming independence of the rules, the probability of overall Type-I error when all the four rules are used simultaneously is |
| A. | 0.101 |
| B. | 0.201 |
| C. | 0.001 |
| D. | 0.301 |
| Answer» B. 0.201 | |