1.

Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the projectActivityDuration (days)1-222-314-331-432-533-524-54The critical path (CP) in the network is

A. 1-2-3-5
B. 1-4-3-5
C. 1-2-3-4-5
D. 1-4-5
Answer» C. 1-2-3-4-5