Find the expected time of an activity with Pessimistic time (tp) = 14 days, Most likely time (tm) = 8 days, Optimistic time (to) = 2 days. |
| A. | 6 |
| B. | 7 |
| C. | 8 |
| D. | 9 |
| Answer» D. 9 | |