Estimates of a water supply project depends upon the rate of water supply per capita consumption and probable population estimated at the end of the design period of |
| A. | none of these. |
| B. | 5 to 10 years |
| C. | 10 to 15 years |
| D. | 15 to 20 years |
| Answer» E. | |