1. |
Earliest finish of an activity is always%! |
A. | Greater than earliest event time of the following node |
B. | Less than earliest event time of the following node |
C. | Less than or equal to earliest event time of the following node |
D. | Greater than or equal to earliest event time of the following node |
Answer» D. Greater than or equal to earliest event time of the following node | |