*/*_Earliest finish of an activity is always? |
| A. | Greater than earliest event time of the following node |
| B. | Less than earliest event time of the following node |
| C. | Less than or equal to earliest event time of the following node |
| D. | Greater than or equal to earliest event time of the following node |
| Answer» D. Greater than or equal to earliest event time of the following node | |