MCQOPTIONS
Saved Bookmarks
1. |
Earliest finish of an activity is always_______________? |
A. | greater than earliest event time of the following node |
B. | less than earliest event time of the following node |
C. | less than or equal to earliest event time of the following node |
D. | greater than or equal to earliest event time of the following node |
Answer» D. greater than or equal to earliest event time of the following node | |