| 1. |
Earliest finish of an activity is always_______________? |
| A. | greater than earliest event time of the following node |
| B. | less than earliest event time of the following node |
| C. | less than or equal to earliest event time of the following node |
| D. | greater than or equal to earliest event time of the following node |
| Answer» D. greater than or equal to earliest event time of the following node | |