Duration along the critical path defines which of the following ?1. Shortest duration needed2. Shortest duration permissible3. Longest duration needed4. Longest duration permissibleSelect the correct answer using the code given below :

A. 1 and 2 only
B. 1 and 4 only
C. 2 and 3 only
D. 3 and 4 only
Answer» C. 2 and 3 only