_Crash project duration is obtained by summing the$? |
A. | Normal durations for all the activities |
B. | Crash durations for all activities |
C. | Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities |
D. | Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities |
Answer» E. | |